Does Davis-Bacon apply to a RAD conversion?
In a public housing RAD conversion, Davis-Bacon prevailing wages apply to work in the Financing Plan and RCC that counts as development (remodeling that changes the units, reconstruction, or a substantial upgrade of original equipment) started within 18 months after the HAP effective date, at projects with nine or more assisted units. Routine like-for-like replacement is exempt.
Prevailing wages are one of the larger swing factors in a RAD budget, and the rule is narrower than many people assume. It turns on three questions: is the work “development”, when does it start, and how many assisted units does the project have.
The rule for public housing conversions
The RAD notice (§1.4.A.14) applies the Davis-Bacon prevailing wage requirements, including the Contract Work Hours and Safety Standards Act and implementing rules, “to all Work, including any new construction, that is identified in the Financing Plan and RCC to the extent that such Work qualifies as development.”
“Development” for Section 8 projects means work that is:
- remodeling that alters the nature or type of housing units in the PBV or PBRA project, or
- reconstruction, or
- a substantial improvement in the quality or kind of original equipment and materials,
and that is initiated within 18 months following the effective date of the HAP contract.
It does not include replacing equipment and materials worn out by normal wear and tear with items of substantially the same kind. And Davis-Bacon applies “only to projects with nine or more assisted units.”
Decision table
| Situation | Davis-Bacon under RAD? |
|---|---|
| Public housing conversion, 9+ assisted units, gut rehab or unit reconfiguration in the Financing Plan, started within 18 months of the HAP | Yes |
| Same, new construction on site or at a transfer site | Yes |
| Like-for-like replacement (roofs, boilers, windows of the same kind) for normal wear and tear | No, not development |
| Substantial upgrade in kind or quality of equipment (for example, new central air where there was none) | Yes, if started within 18 months of the HAP |
| Work in the Financing Plan first started more than 18 months after the HAP | No under RAD’s rule |
| Project with 8 or fewer assisted units | No under RAD’s rule |
| Conversion with no rehab scope (the HAP is signed, no Work) | No |
| Component 2 (Mod Rehab, Rent Supp, RAP, 202 PRAC): signing the HAP | No |
| Component 2: construction or rehab on 9+ units that were not previously assisted or rent restricted and become assisted through the conversion (including by transfer of assistance) | Yes, for those units |
| Any deal using FHA insurance, HOME, CDBG or another source with its own labor rule | Check that source; it can apply independently |
Component 2 is different
For Mod Rehab (Section II of the notice), Rent Supplement and RAP (Section III) and 202 PRAC (Section IV), HUD says execution of the new PBV or PBRA contract “does not trigger Davis-Bacon prevailing wage requirements”. The exception is construction or rehab on nine or more units that were not previously rent assisted or rent restricted and will be newly assisted because of the conversion. For Rent Supp and RAP, the owner must certify in the project description that Davis-Bacon wages will be paid on such units. For PBRA, HUD applies Davis-Bacon to the same extent it would for a PBV conversion. See the Component 2 guide.
Section 3
Section 3 of the Housing and Urban Development Act of 1968 aims hiring and contracting at low-income people and businesses. Under §1.4.A.15 of the RAD notice:
- pre-development conversion costs paid with public housing funds follow Section 3’s public housing rules; and
- any Work required by the conversion after RAD closing that involves housing rehabilitation or construction follows Section 3’s housing and community development rules.
HUD notes that most RAD conversions do not use funding covered by Section 3 on its own terms, which is why it set the post-closing rule as an alternative requirement.
How it shows up in the data
In HUD’s RAD Resource Desk data as of October 24, 2026, the 1,955 closed public housing conversions break down by reported hard cost per unit:
| Hard cost per unit | Closed deals |
|---|---|
| None reported | 438 |
| Under $25,000 | 501 |
| $25,000 to $75,000 | 238 |
| $75,000 or more | 778 |
Of those deals, 367 included new construction and 240 a transfer of assistance; 452 had one or both. Only 18 had fewer than nine total units. The pattern matters because the low-cost deals are the ones most likely to be like-for-like repairs, while new construction and heavy rehab are squarely “development”. The median hard cost across deals that reported it was $78,428 per unit. Every deal’s figures are in the tracker and the financing breakdown.
Budget effects
Davis-Bacon affects a RAD deal in three places:
- Hard costs. Wage determinations for the county and construction type set minimum wages and fringes. The effect depends on how far local market wages sit from the determination, so estimate it from your contractor’s bids under both scenarios, not from a rule of thumb.
- Soft costs and schedule. Certified payroll, posting, interviews and monitoring add contractor and owner administration, and HUD or the lender reviews compliance before draws.
- Feasibility. 4C’s feasibility tests still apply: the Financing Plan must address all critical, immediate and two-year capital needs from the CNA and fund 20-year needs. Higher hard costs raise the gap that tax credits, seller financing or soft funds have to fill.
The 18-month clock creates a planning choice that HUD’s rule allows but does not invite gaming: work genuinely scheduled after month 18 is outside RAD’s definition, but the Financing Plan and RCC define the Work, and lenders and HUD review the schedule. A Financing Plan should state the wage assumption plainly.
Financing affects coverage too. Other sources in the capital stack, such as FHA mortgage insurance for new construction or substantial rehab, HOME or CDBG, can carry their own prevailing wage rules, so confirm each source separately from RAD’s test. The FHA 221(d)(4) guide and FHA 223(f) guide describe the loan types, and the Financing Plan checklist lists the labor items HUD asks for. For a second look at a budget, Janover Capital LLC’s desk is at get financing.
Related: RAD conversion steps, RAD glossary, what is RAD.
Sources
- HUD, RAD Notice Revision 4 as amended by Supplementals 4B and 4C: §1.4.A.14 (Davis-Bacon), §1.4.A.15 (Section 3), §2.5.I and §2.6.F (Mod Rehab), Section III (Rent Supp and RAP), Section IV, paragraph R (202 PRAC).
- HUD, RAD Supplemental Notice 4C, H-2025-01 / PIH-2025-03, §X (feasibility).
- HUD, Revised RAD Notice in the Federal Register, October 10, 2019 (FR Doc. 2019-22134).
- HUD’s RAD Resource Desk data as of October 24, 2026, tabulated by Conversion Ledger.
This guide is general information, not legal advice. Wage coverage on a specific project should be confirmed with HUD, your lender and labor counsel.
Short answers
Does Davis-Bacon apply to RAD conversions?
Often, but not always. For public housing conversions it applies to Financing Plan and RCC work that qualifies as development and starts within 18 months after the HAP contract takes effect, at projects with nine or more assisted units. Like-for-like replacement for normal wear and tear is not development.
Does Davis-Bacon apply to RAD new construction?
Yes, new construction identified in the Financing Plan and RCC is covered when the project has nine or more assisted units, because the RAD notice applies Davis-Bacon to all qualifying Work including any new construction.
Does Davis-Bacon apply to RAD for PRAC or Mod Rehab conversions?
Signing the new HAP contract does not trigger it. It applies only where construction or rehab is done on nine or more units that were not previously assisted or rent restricted and become assisted through the conversion, for example through a transfer of assistance.
Does Section 3 apply to RAD?
Yes. Pre-development costs paid with public housing funds follow Section 3's public housing rules, and any Work required by the conversion after closing that involves rehabilitation or construction follows Section 3's housing and community development rules.
Does a tax credit or FHA loan add its own wage requirement?
It can. Other funding sources carry their own labor rules, so a deal may be covered by Davis-Bacon through FHA or HOME even where RAD alone would not require it. Check each source in the Financing Plan.